Ship Repairs

State of Ship Under Repair/Renovation:

 

S.N Name of the Ship/Craft and Owner 
Name of the OwnerDate of DockingDate of Undocking
Date of Delivery
% Work Done
 
 Remarks 
Arrival   Docking  Undocking Completion 
1. 

 BNS MEGHNA

Bangladesh Navy

 - 27 Apr 2016  17 Sept 2016  18 Sept 2016   97%  
2. 

 LCVP-011

Bangladesh Navy

 -  28 Jul 2016  25 Sept 2016 28 Sept 2016  100%  Delivered 
3. 

 LCT-102

Bangladesh Navy

 - 01 Aug 2016 27 Sep 2016 25 Sep 2016 100% Delivered
4. 

 BNS SURMA

Bangladesh Navy

- 20 Aug 2016  NYF  20 Nov 2016 60%  
5.   MT KOEL - 28 Aug 2016  19 OCt 2016 02 Oct 2016  100% Ready for Delivery
6. MV AGOILJHARA-11 - 06 Sep 2016 07 Nov 2016 10 Nov 2016 60%  
7. FV MATADOR - 15 Sep 2016 17 Oct 2016 17 Oct 2016 100% Delivered
8.

LCT - 101

Bangladesh Navy

- 06 Oct 2016 20 Nov 2016 25 Nov 2016 65%  

 

 

Contact Us

Have query on any issue related to Khulna Shipyard? Want to know more about KSY? Just feel free to contact us.

Connect with Us

We're on Social Networks. Follow us & get in touch.

Site Visited

TodayToday19
YesterdayYesterday101
This WeekThis Week298
This MonthThis Month2066
All DaysAll Days127400